Roundabout at Westwood Drive and Tenterfield Drive, Burnside Heights

  • Project scheduleStart December 2024 with an expected completion February 2025

We are upgrading the intersection of Westwood Drive and Tenterfield Drive, Burnside Heights, by constructing a new roundabout.

A new roundabout will improve traffic flow on Westwood Drive and improve safety of right turns in and out of Tenterfield Drive.

Construction of the roundabout commenced in December 2024 and is expected to be completed by February 2025.

Works will include:

  • new roundabout constructed at the intersection of Westwood Drive and Tenterfield Drive, Burnside
  • upgrade of pedestrian refuge islands on Westwood Drive and Tenterfield Drive

Project updates

Tenterfield Drive is open to traffic but will operate as a left in and left turn out only intersection until Friday 7 February when the final roundabout will be in place.

29 January until 6 February
Left in and left out only at the intersection.
Night time closure of Tenterfield Drive on the night of 5 February for final asphalting and line marking.  See the detour map below

7 February
Intersection operating as a roundabout.

Frequently asked questions

What are traffic impacts during construction?

During the works, we plan to keep Westwood Drive open to traffic. Tenterfield Drive will be closed at the intersection during the school holiday period in January 2025 with detour plans in place. Some weekends and night works will be required when it is necessary.

Roadside electronic message boards and updates on our website will notify the wider community of traffic changes.

How do I stay informed about these works?

Changes in traffic conditions will be communicated through roadside electronic message boards and our website.

What will the roundabout look like?