Cobblebank Stadium

  • Project value$31ml
  • Project scheduleConstruction commenced March 2020, scheduled completion late 2021
Cobblebank-exterior.jpg

The new Cobblebank Stadium is a multi-purpose community facility to respond to the growing need for additional indoor courts within Melton Township.  The new indoor stadium will increase community participation and provide greater access for a range of sports including basketball, netball, badminton, table tennis, volleyball, futsal, school curriculum and community health and wellness programs. 

The project included:

  • six indoor high-ball courts (including show court and seating)
  • Player, referee and public amenities
  • Administration and reception
  • Flexible meeting and social spaces
  • Kiosk and seating areas
  • Car parking

The six-court stadium has been designed to maximise natural light, minimise energy consumption, use environmentally sustainable materials, and use renewable energy.

It features high level thermal insulation, large double-glazed windows, solar panels, and efficient ventilation systems throughout, and will be powered by a 100 per cent renewable energy supply.

There are also water efficient bathroom fittings, as well as rainwater tanks which will be used to water the indigenous plants in the landscaping, and to flush the toilets.

In the car park, visitors with electric vehicles can charge their car, and those who choose to ride their bike can fill their tyres or tighten their brakes at the bicycle repair station.

During the build, sustainable and recyclable materials including timber and steel products have been sourced from environmentally certified and responsible suppliers. Concrete mixes have been made using recycled water and cement that requires significantly less greenhouse gas emissions to produce than traditional Portland cement. Low chemical paints, adhesives, sealants, and carpets were also selected for the build.

Environmental management systems have been in place throughout construction, with contractors actively diverting construction waste away from landfill, and prioritising staff training and wellbeing practices.

Location: Corner of Ferris and Bridge Roads, Cobblebank

Schedule: Construction commenced March 2020
                    Facility open November 2021

Construction updates:

April 2020 - Site establishment, site clearing and earthworks complete

October 2020 - Structural steel and roofing are now well underway with the majority of the pre cast panels in place.

January 2021 - The structural steel and pre-cast panels are complete for all six courts, the framing, plaster and services rough-in are also finished in the player change areas, and the roofing, façade and services rough-in are well underway in the court areas.

May 2021 - Sports flooring being laid

August 2021 - Sports flooring complete and landscaping is progressing

November 2021 - Open and basketball competitions commenced.